Your WIP schedule after an ERP migration: keeping surety and bonding history consistent

By the Junction team · Published 18 November 2026 · 6 min read

The short answer

Your surety and your bank read your WIP schedule closely. When you change accounting system in the middle of the year, that schedule has to keep making sense. This guide covers where continuity breaks, shows it with a made-up example, and gives a checklist. It is practice advice, and not legal or accounting advice.

What does a WIP schedule need for each job?

For each open job a WIP schedule needs the contract value, the estimated total cost, the cost to date and the amount billed to date. From those it works out percent complete, earned revenue and the over or under billing. If any one input is missing or split across systems, the whole row is wrong.

  1. Percent complete = cost to date divided by estimated total cost.
  2. Earned revenue = percent complete multiplied by contract value.
  3. Over or (under) billing = billed to date minus earned revenue.

This is the standard cost-to-cost method. Your accountant may use another, so check. The full walk-through is in how to read a WIP schedule.

Why are jobs that straddle the cutover the risk?

A job that started before cutover and finishes after it has cost and billings in both systems. A report from either one shows only part of the job. Jobs that start and finish on one side are easy. The straddlers are where cost to date, and so earned revenue, can quietly go wrong.

Two things make it worse. First, firms often load only a limited window of history into the new system. A Sage partner says historical migration usually consists of two years of data (Baker Tilly), so older years stay behind. Second, a bank or surety may want to look at earlier years too. What they want is for them to say, so ask them.

What does one straddling job look like?

Take one job, Job 3150, with made-up figures. The contract is $2,000,000 and the estimated total cost is $1,600,000. At cutover the old system holds $700,000 of cost and $800,000 billed. Since cutover the new system holds $300,000 of cost and $500,000 billed. Work through the three steps, three ways.

Job 3150 (made up)Old system onlyNew system onlyBoth combined (right)
Contract value$2,000,000$2,000,000$2,000,000
Estimated total cost$1,600,000$1,600,000$1,600,000
Cost to date$700,000$300,000$1,000,000
Percent complete43.75%18.75%62.5%
Earned revenue$875,000$375,000$1,250,000
Billed to date$800,000$500,000$1,300,000
Over or (under) billed$75,000 under$125,000 over$50,000 over

The right answer is $50,000 overbilled. The old system alone says $75,000 underbilled, which is a swing of $125,000 and the wrong sign. The new system alone says $125,000 overbilled, which is $75,000 too high. Both are accurate reports of their own system. Neither is the job.

How do you keep the WIP schedule consistent across the switch?

Treat each straddling job as one job with two sets of figures that you add together, and prove the total before you send a schedule out. Agree how cost codes line up, tie the loaded balances to the old system, and keep the old system reachable. The checklist below puts it in order.

  • Ask first. Ask your surety and bank what history and format they want, and whether they want the switch explained. Do not assume.
  • List the straddlers. Every job open at the cutover date, with cost and billed in the old system at that date.
  • Fix the estimate. Decide who owns the estimated total cost for each job after cutover, and when it is next reviewed.
  • Match the codes. Use one mapping between old and new cost codes; see mapping cost codes.
  • Tie out. Compare cost to date and billed to date for each job against the old system; the tie-out checklist has the steps.
  • Run a parallel close. DualEntry describes closing one period in both systems and keeping the legacy one until they reconcile.
  • Save the last old schedule. Keep the final WIP schedule from the old system as a file, with the date and who ran it.
  • Add a note. Put a short note on the first combined schedule saying which jobs span both systems and how the figures were added.

A consulting firm writing about Dynamics GP describes merge views that blend old history with new transactions to support continuous reporting across the cutover, with controls against double counting (RSM). That is the same idea, whichever way you build it.

How can you check a straddling job without a spreadsheet?

With both systems connected to an MCP connector, you can ask your AI assistant for a job's cost and billing from each system, then for the total. It shows which system each figure came from, so you can compare it with your schedule. Check the first answers by hand against the example above.

Questions for a job that spans both systems

  • For job 3150, show cost to date and billed to date in the old system and in the new system, then the combined total.
  • Using the combined figures, what are percent complete, earned revenue and over or under billing for job 3150?
  • Which jobs open at the cutover date have cost in both systems?
  • For each of those jobs, how far does the over or under billing change if only the new system is used?

The wider approach, including the five ways to bridge two systems, is in reporting across old and new ERP during a migration. Your surety and bank may also ask about earlier periods later on; see old ERP data for audits and due diligence.

Frequently asked questions

What happens to my WIP schedule after an ERP migration?
For jobs that start and finish on one side of the cutover, nothing changes. For jobs that straddle it, cost and billing sit in two systems and must be added together, or percent complete and over or under billing will be wrong.
What does a surety want to see in a WIP schedule after a system change?
It varies by surety, so ask yours. In practice, expect questions about consistency between old and new figures. This guide does not state any requirement.
How many years of job history should the new system hold for bonding?
Ask your surety and bank. The answer differs between them, and between firms. Once you know, check whether your migration loads that many years, and plan to reach the old system for the rest.
How do you calculate percent complete for a job split across two ERPs?
Add cost to date from both systems, then divide by the estimated total cost. Multiply by contract value for earned revenue, and subtract that from total billed to date. Using one system alone gives the wrong answer.
Should you keep the old ERP running for WIP history?
Keep the old data reachable for as long as your surety, bank, auditor and counsel say they may ask for it. Whether that means the live application, a copy or saved reports is for you and them to agree.

Sources