ERP cutover checklist for construction controllers: before, during and after

By the Junction team · Published 18 November 2026 · 6 min read

The short answer

A cutover is the date the new system becomes the system of record. For a contractor it is the riskiest week of the migration, because jobs, subcontracts and billings do not pause while you switch. This is a working checklist for the controller. Items marked as practice advice come from experience, not from a vendor.

When should you choose the cutover date?

Choose a period end, ideally a month end that is not also a quarter or year end, and not in the middle of a payroll cycle or a large billing run. A clean period end gives you one closing trial balance to tie to, and a clear line between old and new.

Most finance teams run a parallel close, closing one period in the old and the new system side by side, and keep the old system until both closes reconcile (DualEntry). So the date you pick needs a period after it that you are willing to close twice. For how both systems are reported while that happens, see how to report across old and new ERP.

What should you do before cutover?

Before cutover, settle what moves, map the cost codes, agree the checks and the sign-off, and decide how old history will be reached. Doing this early turns the cutover week into a run of checks rather than a series of decisions made under pressure.

  1. Decide what moves and what stays behind, using what job cost data to migrate and what to leave behind.
  2. Map every cost code you will keep, and list those you will retire (how to map cost codes).
  3. List every open job, open subcontract and open purchase order, with the committed cost on each (practice advice).
  4. Agree who signs off each check and what variance is acceptable (practice advice).
  5. Decide how old history will be reached after the old system is retired, and write it down.
  6. Confirm the payroll calendar so no pay run straddles the cutover (practice advice).

What should you do during cutover?

During cutover, freeze the old system, close the final period in both, tie opening balances to the old trial balance, and compare open jobs. Nothing should be posted to the old system after the freeze except corrections that you also record in the new one.

  1. Freeze the old system: stop new postings and record the freeze time.
  2. Close the last period in the old system and the same period in the new one.
  3. Tie opening balances to the legacy trial balance as of the cutover date. DualEntry says to match it to the dollar.
  4. Check open accounts receivable and open accounts payable against their sub-ledger totals, and cash against the last bank reconciliation, as the same source describes.
  5. Compare every open job: cost to date, committed cost, billed to date and retainage held and owed (practice advice).
  6. Rebuild the WIP schedule from the new system and compare it with the last one from the old. The WIP guide shows what to look for.
  7. Check each payroll cycle that touched both systems, including burden and union fringes (practice advice).

The step-by-step tests for job cost and WIP are in the job cost and WIP tie-out checklist.

What should you do after cutover?

After cutover, close the first full period in the new system, reconcile it against what the old system would have shown, record every difference with its cause, and only then retire the old system. Keep old history reachable for audits, sureties and questions about jobs that started before the date.

  1. Close the first period in the new system and compare it with the old system's last close.
  2. Log every difference and its cause. Unexplained differences stop the go/no-go.
  3. Test that someone can answer a question about a pre-cutover job from the old history, the way you agreed.
  4. Brief your surety and auditor on the cutover date and where each side of it lives (surety and bonding guidance).
  5. Agree the date the old system is switched off, and what is kept: see keeping access to legacy data.
  6. Switch off, and record who agreed.

Who owns each step?

Each step needs one named owner and one person who signs off. As a rule of thumb, accounting owns the closes and balances, project controls owns jobs and WIP, IT owns the freeze and the old system, and the CFO or controller makes the go or no-go decision on variances.

StepOwnerSigns offEvidence to keep
Choose cutover at a period endAccountingCFOThe calendar and the reasoning
Freeze the old systemITAccountingFreeze time and a list of who has access
Close in both systemsAccountingControllerTwo trial balances for the same period
Tie opening balances and sub-ledgersAccountingControllerTie-out sheet with each difference explained
Compare open jobs, committed cost and retainageProject controlsControllerA list of jobs with the old and new figures side by side
WIP schedule rebuilt and comparedProject controlsCFOBoth WIP schedules and the explained differences
Payroll cycles checkedAccountingControllerPay run totals for each cycle that touched both
Go or no-go on variancesControllerCFOThe decision, dated and recorded
Switch off the old systemITCFODate, what was kept, and who can reach it

Frequently asked questions

What should be on an ERP cutover checklist for a construction company?
Period-end timing, a freeze of the old system, a close in both systems, opening balances tied to the old trial balance, AR and AP sub-ledgers, open jobs, committed cost, retainage, WIP, payroll cycles, sign-off, access to old history and a switch-off date.
When is the best time to cut over to a new construction ERP?
At a period end, usually a month end that is not a quarter or year end, and away from a payroll cycle or big billing run. A clean period end gives one trial balance to tie to. Your controller and auditor should confirm the date.
What is a parallel close in an ERP migration?
It is closing one period in both the old and the new system side by side and reconciling them. Finance guides commonly say to keep the old system until both closes reconcile.
Who should sign off an ERP cutover?
Accounting closes and ties out, project controls checks jobs and WIP, IT freezes and switches off, and the CFO or controller makes the go or no-go call on variances. Write down who signs each step before the cutover week starts.
How long should you keep the old ERP after cutover?
Keep it until the first closes reconcile and every difference has a recorded cause. After that, keep the history reachable, as an archive or a connection, for as long as audits, sureties and warranty questions need it.